Week of March 26, 2018 Work Completed 03/26 – 03/30: Focus Construction started sheathing around the perimeter of the site. Upcoming public way closures for site utility work will be...
Week of March 19, 2018 Work Completed 03/19 – 03/23: Focus Construction has finished pouring caissons on site, and is getting ready to haul off Subtitle D material, along with...
Week of March 05, 2018 Work Completed 03/05 – 03/09: Focus Construction has start to drill and pour Caissons on site. Between 20-24 caissons have been poured this week. Work...
Week of February 26, 2018 Work Completed 02/26 – 03/02: Potholing on site is complete, along with the preparation of the pad for the caissons. Neighbors have been issued a...