Work Completed 10/08 – 10/12: Focus Construction finished prepping the level 02 deck, and lower swimming pool deck with beams and precast. The topping slab for the lower pool and...
Work Completed 10/01 – 10/05: Focus Construction finished erecting the precast plank for level 2. Once the plank was set, the in-slab conduit, grout, and rebar was placed in preparation...
Work Completed 09/24 – 09/28: Focus Construction finished erecting the beams for Level 02, while installing grade level ceiling conduit, and electrical rough and prep for level 02. Once the...
Work Completed 09/17 – 09/21: Focus Construction finished pouring the topping slab for the west half on the mezzanine level deck, and is getting ready to pour the east half,...
Work Completed 09/10 – 09/14: Focus Construction finished backfilling the site, setting up shoring for the mezzanine level deck, and erecting the precast plank for the mezzanine level. The precast...
Work Completed 09/04 – 09/07: Focus Construction continued waterproofing the perimeter of the site, as well as backfilling the site. Focus construction also began detailing the stair wells and plank...
Work Completed 08/27 – 08/31: Focus Construction finished pouring the 10 foot strip of concrete in the basement that was required in order to backfill the perimeter of the site....
Work Completed 08/20 – 08/24: Focus Construction finished pouring the topping slab for the ground level on the east and west halves. While the topping slabs were poured, the beams...
Work Completed 08/13 – 08/17: Focus Construction finished prepping the ground level for concrete topping, including all the box outs for the exterior columns, welding all rebar to embed plates,...
Work Completed 08/06 – 08/10: Focus Construction finished installing the precast plank for the ground level, while modifying changes in order to get ready to pour the topping slab for...